How to install SS1.5

Modified on: Fri, Mar 14 2025 11:59 AM

PURPOSE

Explains how to replace a Send Station with a Send Station 1.5 at a site.


PROCESS

  1. The old Send Station is in the IT Cabinet and is a Blue box.
    • NOTE: It should have a label that says send station on the front.
  2. Plug the VGA to Display port adapter into the Dell 7010 PC.
  3. Plug the 6 ft black VGA cable into the cable you attached in the step above. 
  4. The other end of the VGA cable goes into the KVM console replacing the old Send Station VGA cable.
  5. Remove the ethernet cable from the old Send Station computer and plug it into the Dell 7010 computer.
  6. Remove the USB cables from the old Send Station compute and plug them into the Dell 7010 computer.
  7. Using the call tag, send the old Send Station (Blue Rack Mount PC) back to HQ.
  8. Move the Adderlink cables highlighted below to the new Send Station computer.
  9. This is what the send station should look like at the end. Touch screen, video cables, network cable should only be connected.
  10. Order the following Hope Industrial enclosure on HotShop.
    • Item number: ENCL-TC01-SS4-L2
  11. After receiving the Hope Industrial enclosure, follow the instructions below.


HISTORY

Revised Date Revised By Revisions 
Unknown Unknown Document created
12/30/2021 Karl Futscher Document checked for sensitive credentials
10/20/2023 Yolanda Terrazas-Franco Format updated and grammar mistakes fixed.
8/14/2024 Andrew Poskey Moved to Fresh
3/14/2025 Andrew Poskey Updated title and content formatting

 

Was this answer helpful?